Building No.1

REALIZATION OF PREFAB OFFICE MTT KTTC LNO

-Inside Singara camp in IT-NCC LAND-ERBIL

 Details:

This project aims at the creation of fixed structures 1 main buildings that consist of 4 big offices, by sandwich panel and steel structure system double roofing

With all electrical and LAN system for all offices

Total time for completed this project 3 weeks

Total area 90 m2

 

 

 